On July 27th, 2020, Vietranstimex successfully received and transported the 220kV-250MVA Transformer (11830mm x 3230mm x 3620mm) of 140 tons and associated fuels and fittings of 95 tons from 220kV Than Uyen Substation (Lai Chau) to 220kV Thuy Nguyen Substation (Hai Phong). The Project marks the cooperation between Vietranstimex and Power Transmission Company N01 (PTC1).
The handling and lifting of the transformer was executed at Than Uyen Substation in July 20th, 2020 while the transportation and delivery to PTC1 was finished on July 27th as schedule.
With the whole distance up to 485km across 9 provinces/cities (Including Lai Chau, Yen Bai, Vinh Phuc, Hanoi, Bac Ninh, Hai Duong, Quang Ninh, Hai Phong), Vietranstimex has conducted surveys, calculations and prepared the appropriate plan to ensure in-time transportation, as well as ensuring the compliance to safety procedures in lifting and transporting oversize-overweight loads.
Congratulations to Vietranstimex and PTC1. Wishing the two sides’ cooperation huge success!