Vietranstimex received transportation for Lac Hoa 2 Wind Power Project, Soc Trang with a total volume of 40 sets of project equipment including Nacelles, blades and wind turbines divided into 5 big shipments. The entire volume will be waterway transported by barges, received at Lotus port, District 7, Ho Chi Minh City, and continue to be transported to Lac Hoa 2 wind power site, Soc Trang province.
Various means of transport from small potons, tunnel barges to large potons with a length of up to 92m.
From November 24 to December 12, 2021 (19 days), completed 18 barges, released all 08 sets of wind power from Lotus Port
The project was completed by the end of March 2022 (91 barges trips).