Subsea Skid weighing 215 tons (dimension: 20m x 8.3m x 8.1m) of the MERO Project Phase 3 at Dong Xuyen Port, Vung Tau.
The sitemove at the factory started at 04:30AM and finished loading out at 08:00AM.
The remaining works such as pumping water in for sailing and cleaning up were also urgently finished right after that to complete the entire job within the same day.
Vietranstimex mobilized a convoy of self-propelled hydraulic trailers SPMT (Self-propelled Modular Transporter) with 24 axles and 2 heads of PPU Commetto, 10 ballast pumps, 04 hydraulic winches and some other tools and supplies, carried out detailed calculations on stability, lashing, load distribution, ... fully comply with regulations and ensure site safety when performing.